The Simo solar farm will contain around 120,000 solar panels, for which JIITEE Työt carried out the foundation work by drilling 23,016 holes in the ground.
"We spent a day in December 2024 doing test drilling, with the actual contract period running from January 13 to April 28, 2025, including all necessary repair work. In total, the project took 106 days, with the drilling completed in just 87 days, which is quite a feat considering the number of holes that had to be drilled in harsh conditions," says Valtteri Aurio, foreman at JIITEE Työt.
Work was carried out seven days a week during the project, with the work scheduled between 6 a.m. and 10 p.m. because of noise restrictions. The work progressed as planned throughout the project. Aurio explains: "Throughout the project, work was only interrupted on three days for equipment maintenance. Apart from that, we carried out all the basic maintenance between drilling operations, which helped avoid major work interruptions and was crucial to keeping the project on track.”
An Atlas Copco Smartroc D65 drill rig was used for the work, and the standard crew included a driller, a surveyor and a foreman. In addition, hourly workers were also on site when needed by the main contractor to assist with tasks such as ensuring that the holes remained open and preventing them from freezing.
"We were able to react quickly to the need for additional labor, ensuring that the required number of workers were available on the worksite the very next day,” says Aurio.
During the project, holes were drilled in all weathers, even in sub-zero temperatures. The temperature dropping 25–30 degrees below zero did not stop the work, and the machines were kept running late into the night to ensure that the equipment stayed operational. "During the coldest days, we were the only ones working on the site,” says Aurio, noting that the project was completed on schedule.